Availability, performance, quality and OEE worked out from the raw numbers.
Your figures
Keep units consistent: kg with kg, minutes with minutes. Results update as you type.
OEE
—
Availability
—
Performance
—
Quality
—
Run time
—
Formula
Availability × performance × quality, where availability = run time ÷ planned time, performance = ideal cycle time × total count ÷ run time, quality = good count ÷ total count
=((B2-C2)/B2)*((D2*E2)/((B2-C2)*60))*(F2/E2)Excel: B2 planned production time; C2 downtime (unplanned stops); D2 ideal cycle time; E2 total count; F2 good count
World-class OEE is often quoted as 85%. Performance above 100% means the ideal cycle time is set too slow.
Save this calculation
Enter your figures (or try the worked example) to save them.
General calculation. Confirm your site's own definitions, validated limits and specifications before using a result for process control or product release.