Guide6.1
Daily pre-operation checklist
Complete before the first start of every shift. Do not start production with any item failed.
| Check | OK | Check | OK |
|---|---|---|---|
| Emergency stop operational | ☐ | Sensors clean | ☐ |
| Safety doors and interlocks functional | ☐ | Guide tracks clean | ☐ |
| Vacuum pressure normal | ☐ | Vacuum filter clean | ☐ |
| Air pressure normal | ☐ | Nuts and bolts tight | ☐ |
| Lubrication completed | ☐ | No abnormal noise | ☐ |
| Capsule feeder clean | ☐ | No oil leakage | ☐ |
| Powder hopper clean | ☐ | Wiring visually intact | ☐ |
| Dosing disc clean | ☐ | Correct capsule size installed | ☐ |
| Machine cleaned and line cleared | ☐ | Slow-speed test run completed | ☐ |